01 / 05WAREHOUSE · CONSTRUCTION COST REVIEWCHECKED · COST −36%

Warehouse with two overhead cranes

New design in 2 weeks after the inputs changed. Construction cost −36%

footprint
~98 × 164 ft
footprint
crane equipment
2 overhead cranes
crane equipment
incl. client revisions
2 weeks
incl. client revisions
construction cost
−36%
construction cost
Sheet 4. Model by layers: piles, equipment, frame, roof

Real IFC model of the project. Rotate it, cut it, click any element

02SHEETS

03TASK

The warehouse had been designed in 2D over ~4 months. Then the floor area, the design loads, the crane equipment and the geotechnical data changed. The owner needed a buildable design for the new inputs without another long cycle

INPUTS THAT CHANGED

Floor area, design loads, crane equipment and the geotechnical data, all after the original 4-month 2D design

04WHAT WE DID

  1. 1

    Regenerated SD, DD and CD as one model from the revised brief

    every client revision included in one pass

  2. 2

    Re-checked pile capacity and settlement against the geotechnical report

    fewer and shorter piles

  3. 3

    Resized the steel after the design loads were reduced

    lighter sections

  4. 4

    Re-checked the crane runways for the new wheel loads

    deflection and fatigue verified

  5. 5

    Reissued the pile schedule, drawings and bill of materials

    REV A → REV B from the model

05WHAT CHANGED

Design time
~4 months in 2D
Construction cost
original design
Piles
more, longer
Documents
redrawn by hand

More cases

All cases →

New design in 2 weeks. Construction cost −36%